GOOD SHEPHERD CATHOLIC CHURCH
Evansville, Indiana
RESTORATION & REBUILDING COMMITTEE MINUTUES
July 12, 2007
The
meeting of the Restoration &
Rebuilding Committee was held on Thursday, July 12, 2007. Deacon Ed opened the meeting with a prayer at 6:30 p.m.
ATTENDANCE Deacon
ED Wilkerson Mark Schuler
Rita Gallagher Tom Schuler
Tim Henning Bryon
Swader
Mark Logel Judy VanHoosier
Jeff Pate Marilyn
Wassmer
Tom Peake
Ron Pohl
ABSENT Jim Gribbins, Pat Will (vacation)
GUESTS Jimmy Meadows, EE from Biagi Chance Cummins London
Titzer
PARISH HALL – Tim introduced Jimmy
Meadows. Jimmy is the Electrical Engineer assigned to develop lighting and
electrical solutions for our project.
·
Discussion
on whether the currently designed bingo playing space in the Parish Hall will
be large enough to accommodate the anticipated number of players. The first 2
bingo sessions averaged 210 players. Tom Schuler was asked to mark off the 84’x
68’ space in the gym and determine the maximum number of tables (players) that
could be accommodated in that space. Tom plans to do after bingo crew leader
meeting next Monday evening.
·
Discussed
possible lighting schemes for the Parish Hall. Jimmy Meadows stated that the
most effective and efficient lighting is either florescent or metal halide.
Discussed several options but kept coming back to a lay-in ceiling and
associated lay-in florescent lighting fixtures for the majority of the space as
the desired approach. Will also look at some type of track lighting for the
stage area with simple to operate dimming devices. Mark Logel requested that we
use florescent bulbs (green) that will not require any special disposal issues
at end of life. Tim will also include some lighting via some wall mounted
sconces for low lighting needs during evening receptions, etc. Marilyn
requested that there be a number of wall receptacles be installed in the
concession area. Judy asked that there be a number of wall receptacles
available to accommodate the floor buffing equipment as well.
·
Will
need to provide some type of weather protection for bingo smokers. Tim will add
some type of awning along the northwest side of the building.
·
Tim
to add some type of concrete barrier in the dumpster area to prevent the
dumpster from being placed too close or into the building during the trash
pickup process.
·
Tim
was asked again! (just kidding) to move Judy’s office door adjacent to the door
of her administrative teams area.
·
Tom
P. asked if we could just eliminate the door between the kitchen and concession
area altogether to provide easier access between these 2 areas. Agreed on
·
Discussed
several window location schemes. Judy proposed that we install on south wall
only. This would provide the most consistent outside light into the building
during the day. Agreed on
PARISH ADMINISTRATION CENTER
(PAC) – Tom
Peake and Tim Henning plan to attend what is anticipated to be the final
meeting with the Diocesan Building Commission on this building on August 14. At
that time we will also plan to present the first drawings of the proposed
Parish Hall.
COST ESTIMATE AND FUNDING – Brief discussion on funding
and status of capital campaign. Reemphasized that the project included both
buildings and that construction of the PAC would not begin until the capital
campaign goals were met.
·
Tim
provided construction estimates for all of the buildings and they are as
follows:
Parish
Activity Center $ 900,000
Parish
Hall 1,514,000
Pre-School
(Alternate) 718,000
New
School Entrance 100,000
Total
Construction $ 3,232,000
Less Insurance Claim 1,054,000
Capital
Campaign $ 2,178,000
·
Deacon
Ed projected a start date of mid September for the capital campaign kickoff
RESTORATION
·
The
kitchen HVAC is scheduled to be installed the week of July 23, chef’s counter
will be installed next week
·
Received
estimates to install ductless HVAC in teachers workroom and heating units in
the 3 restrooms in the original classroom wing
·
Deacon
Ed, T. Peake, R. Pohl and Sarah Gahagan met with our insurance adjuster team
(Brian Ferguson, Tom Vierling), and Bob Cox and Luke Bohls(spelling?) from the
diocese this morning. Brian and Tom are very impressed that Good Shepherd is
this far along in the restoration and building replacement process in just 7
months. Second insurance payment of $1.8M is in process.
PLAYGROUND DISCUSSION – Mark Logel received
updated information from Laurie Witting and Robin Deem on moving the playground
to the north end of the school. Laurie
and Robin spent a considerable amount of time marking off a potential
playground perimeter that will provide enough area to house existing and
planned equipment. The next step is to provide cost estimates for the project
to Mark to bring back to the committee
The
next meeting of the Restoration and Rebuilding Committee will be held sometime
after the August 14 meeting with the diocese and will be communicated to the
committee members when the date is selected.
Respectfully
submitted,
Tom
Peake